What Happens After Solar Installation: The Commissioning, DNO, and SEG Timeline

Updated 2026-03-259 min read
Completed solar panel installation on a UK home

The installation crew has packed up, the scaffolding is coming down, and there are panels on your roof. Congratulations. But what happens next? There's a surprising amount of admin between "panels installed" and "getting paid for your exports," and most installers don't explain the full timeline clearly. Here's exactly what to expect, week by week.

Week 0: Installation Day and Commissioning

Installation day itself is covered in our solar installation process guide, but the final hours are where your post-installation timeline begins.

What happens during commissioning

Once the panels are mounted, wired, and the inverter is connected, your installer carries out commissioning — a formal set of tests to verify everything is working safely and correctly. This includes:

  • Earth fault loop impedance testing — confirms the earthing is safe and compliant
  • Insulation resistance testing — checks there are no faults in the DC wiring
  • Polarity checks — verifies all connections are the right way round
  • Generation verification — the installer powers up the system and confirms it's producing electricity
  • G98/G99 relay settings — verifies the inverter's grid protection settings are correct

This isn't optional. Commissioning is a requirement of the MCS certification process and must be completed before your installer can issue your certificate.

The handover

Before your installer leaves, you should receive (or be told when to expect):

  • MCS certificate — the single most important document. You need this for SEG registration. Some installers provide it on the day; others post it within 1–2 weeks.
  • Warranty documents — for panels, inverter, and mounting system (these often have different warranty periods)
  • User manuals — for the inverter and any battery system
  • Generation meter reading — your starting point for tracking output
  • Commissioning certificate — the formal record of the tests carried out
  • As-built drawings or schematics — showing the system layout and wiring

Take Photos of Everything

Photograph the inverter serial number, generation meter reading, any labels on the consumer unit, and the system schematic. Store these digitally. If you ever need to make a warranty claim, switch SEG provider, or sell the house, you'll be glad you did.

Can you use your electricity straight away?

Yes. The moment the inverter is switched on and generating, you're producing electricity that feeds directly into your home. Any appliance running at that moment is being powered (at least partially) by solar. You don't need permission from anyone to use your own solar electricity.

However, you are not yet registered to export electricity to the grid. Any surplus power flowing back through your meter during these early weeks is effectively given away for free. This is normal and expected — it's typically only a few weeks' worth of exports.

Weeks 1–2: DNO Notification and WiFi Setup

DNO notification: G98 vs G99

Your installer is responsible for notifying your Distribution Network Operator (DNO) about the installation. Which process applies depends on your inverter size:

G98 (inverter up to 3.68kW per phase): This covers most standard domestic installations. Your installer submits the notification online after installation, and it's typically acknowledged by the DNO within 10 working days. No approval is needed — it's just a notification. You can generate and use your electricity throughout this period with no issues whatsoever.

G99 (inverter above 3.68kW per phase): This is an application, not a notification, and it should have been submitted 4–8 weeks before installation because the DNO has up to 45 working days to respond.

G99 should already be done

If your system has an inverter larger than 3.68kW on a single-phase supply and your installer hasn't already submitted and received a G99 approval before installation day, something has gone wrong. Contact your installer immediately. Operating a larger system without G99 approval can create issues with your DNO and may affect your ability to register for the SEG.

Setting up inverter monitoring

Most modern inverters have WiFi connectivity and a companion app or web portal. Getting this set up in the first week is well worth doing — it lets you see exactly how much you're generating, consuming, and exporting in real time.

Common monitoring platforms by brand:

  • GivEnergy — GivEnergy portal (givmonitoring.com) and app
  • Fox ESS — Fox Cloud (foxesscloud.com) and app
  • Solis — Solis Cloud (solis-cloud.com) and app
  • SunSynk — SunSynk Connect app
  • Growatt — ShinePhone app and server
  • Huawei — FusionSolar app

The setup process is broadly similar for all brands: connect the inverter to your home WiFi (usually via WPS button or AP mode), then register for an account on the manufacturer's portal. Your installer should help with this, but if they don't, the process is usually straightforward with the manual.

WiFi Signal Strength Matters

Inverters are often installed in garages, lofts, or utility rooms where WiFi signal is weak. If your inverter keeps dropping offline, consider a WiFi extender or powerline adapter rather than blaming the inverter. Also check that the CT clamp (the clip-on sensor on your meter tails) is correctly positioned — if it's on the wrong cable or facing the wrong way, your consumption and export readings will be nonsensical.

Weeks 2–4: MCS Certificate and SEG Registration

Getting your MCS certificate

If your installer didn't hand over the MCS certificate on installation day, chase it. You need this document to register for the Smart Export Guarantee (SEG), and there's no workaround. The certificate confirms your system was installed by an MCS-certified installer to the required standards.

The certificate includes your system details, installer details, and a unique reference number. Your installation is also recorded on the MCS database, which SEG providers check during registration.

Registering for the SEG

The SEG is the mechanism by which you get paid for electricity you export to the grid. It replaced the old Feed-in Tariff and requires you to actively register — it doesn't happen automatically.

To register, you'll need:

  • MCS certificate (or MCS installation reference number)
  • Your electricity meter serial number (MPAN for the supply, plus the generation meter serial number)
  • Proof of address
  • Bank details for payment

Popular SEG providers include:

  • Octopus Energy — currently among the highest fixed-rate SEG tariffs, and they offer Agile Outgoing for variable export rates
  • British Gas — straightforward application, quarterly payments
  • E.ON Next — competitive rates, online management
  • EDF — reliable, standard offering
  • Ovo Energy — decent rates with online dashboard

You don't have to use your current electricity supplier for SEG — you can register with whichever provider offers the best rate. Switching SEG provider later is straightforward too.

SEG registration typically takes 2–4 weeks to process. Some providers are faster than others. Octopus tends to be among the quicker ones.

Weeks 4–8: First Export Payments and Finding Your Rhythm

Your first SEG payment

Most SEG providers pay quarterly. Your first payment will likely cover a partial quarter, so don't expect much. A typical 4kW system might export 1,500–2,000 kWh per year, but that's heavily weighted towards the summer months. If you installed in November, your first quarter's exports will be modest.

Don't be discouraged by a small first payment. The real value of solar is in the electricity you use yourself (saving you the full retail rate of 24p+ per kWh), not the electricity you export (which earns you around 4–15p per kWh depending on your tariff).

Learning your self-consumption patterns

This is where monitoring data becomes genuinely useful. After a few weeks, you'll start to notice patterns:

  • Peak generation is typically between 10am and 3pm
  • Highest self-consumption happens when you run appliances during peak generation
  • Export spikes happen when the sun is shining and nobody is home

The simplest way to save money is to shift flexible loads into your generation window: run the washing machine, dishwasher, and tumble dryer during the middle of the day rather than in the evening. No technology needed — just a change of habit.

Month 3 and Beyond: Optimisation

Once you've got a few months of data and the admin is sorted, you can start optimising.

Smart tariffs

If you have a battery system, a smart tariff can significantly boost your savings. Tariffs like Octopus Agile or Intelligent Go offer cheap overnight rates (sometimes as low as 7p/kWh) that you can use to charge your battery, then use that stored electricity during expensive peak periods.

Home automation

For those who want to go further, Home Assistant with the Predbat add-on can automate your battery charging and discharging schedule based on weather forecasts, tariff prices, and your usage patterns. It's not essential, but it can squeeze an extra 10–20% savings out of a battery system.

Your first meaningful SEG payment

By month 3–4, you'll receive your first full quarter's SEG payment and have enough generation data to understand your system's actual performance. Compare your total generation against what was predicted in your installer's quote — most systems perform within 10% of predictions over a full year, but individual months can vary significantly with weather.

Common Problems (and How to Fix Them)

Installer hasn't submitted the DNO notification. This is the most common post-installation complaint. If it's been more than two weeks since installation and your installer can't confirm the G98 has been submitted, chase them firmly. They're required to do this as part of the MCS process. If they remain unresponsive, you can contact MCS directly to raise a complaint.

SEG provider asking for documents you don't have. The usual sticking points are the MCS certificate, the generation meter serial number, and sometimes an EPC (Energy Performance Certificate). Your installer should provide the MCS certificate and meter details. If they haven't, contact them. An EPC is only required by some providers — if yours insists on one and you don't have a recent one, it may be worth switching to a provider that doesn't require it.

Inverter won't connect to WiFi. Check signal strength first — this is the cause in most cases. If the signal is adequate, try connecting via the inverter's AP (access point) mode rather than WPS. Also verify the CT clamp is seated properly on the correct cable and facing the right direction (there's usually an arrow indicating current flow direction).

Generation seems lower than expected. If you installed in autumn or winter, wait before panicking. A system installed in December might generate only 15–20% of what it will produce in June. Compare your actual output against monthly predictions, not annual ones. If generation is low even in good sunshine, check for shading issues, a tripped DC isolator, or an inverter fault code on the display.

Keep a Simple Log

For the first year, note your generation meter reading on the first of each month. This gives you a baseline to compare against in future years and helps you spot any gradual performance issues early. Most monitoring apps provide this data too, but a manual reading from the generation meter is your independent backup.

The Full Timeline at a Glance

MilestoneTypical timing
Installation and commissioningDay 0
System generating electricityDay 0
Inverter WiFi and monitoring set upDays 1–7
DNO notification submitted (G98)Days 1–14
DNO acknowledgement receivedDays 5–20
MCS certificate receivedDays 0–14
SEG registration submittedWeeks 2–4
SEG registration confirmedWeeks 4–8
First SEG paymentMonths 2–4
First full quarter's dataMonth 3–4
System fully optimisedMonth 6+

The gap between installation day and your first SEG payment can feel frustratingly long, but it's standard. The good news is that your system is saving you money from the moment it's switched on — every kilowatt-hour you generate and use yourself is one you don't buy from the grid. The export payments are a bonus, not the main event.

Share this article

OVO Solar & Heating
OVO Solar & HeatingTrusted UK installer

OVO has carefully selected trusted teams across the UK to install solar panels and heat pumps. Enjoy the personal touch of a local expert with the peace of mind of a household name.

Get a free quote from OVO

Affiliate link — we may earn a small commission at no extra cost to you

Stay informed

Get free solar updates direct to your inbox

Free updates on tariffs, grants & solar news. No spam, ever.

Related reading

What does this mean for YOUR home?

Design your perfect solar setup in under 3 minutes. Free, no sign-up required.

Build Your Solar System